    Program Evaluation and Review Technique (PERT)

    PERT is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates
    PERT uses probabilistic time estimates
    duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations, or a three-point estimate

  • #3002 Reply

    Mandy

    Program Evaluation and Review Technique (PERT) is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates.
    PERT weighted average =
    (Optimistic time + (4 × Most likely time) + Pessimistic time) / 6