Calculating the Critical Path

1-First develop a good network diagram

2-Add the duration estimates for all activities on each path through the network diagram

3-The longest path is the critical path

4-one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action